VKG Oil AS — Process Piping Infrastructure for PETROTER 1, 2, and 3 Plants

Process piping design for retort gas, natural gas, steam, feed water, and heating water from PETROTER 1, 2, 3 plants to power stations.

Project Overview

Development of complete engineering design for interplant utility and process piping interconnecting PETROTER 1, 2, and 3 oil shale processing plants with VKG Energia power stations. Scope included high/low-pressure retort (shale) gas pipelines, natural gas, high-pressure steam, feed water, and district heating mains.

Key Specifications

  • Client: VKG Oil AS
  • Facilities: PETROTER 1, 2, 3 processing plants and thermal power plant
  • Media: Retort gas, natural gas, superheated steam, feed water, heating water
  • Scope: Detailed design of process piping racks and interplant distribution networks