Project Overview

Mechanical installation, piping integration, and tuning of six 20 MW ENTEH-VTI dual-fuel burners (total capacity 120 MW) on a newly installed E-135 steam boiler. The burners ensure high-efficiency co-firing and single-fuel firing of process gas and liquid fuel, delivering low emissions and high flame stability across all operational loads.

Key Specifications

  • Client / Facility: VKG Energia OÜ
  • Boiler Unit: Steam boiler E-135
  • Burner Type: ENTEH-VTI dual-fuel burners
  • Quantity & Capacity: 6 burners × 20 MW (120 MW total)
  • Scope: Equipment installation, fuel/air piping integration, commissioning, and combustion adjustment