Enefit Power AS — TP-101 boiler reconstruction with four ENTEH Low-NOx pyrolysis gas burners (45 MW each)

TP-101 boiler reconstruction with four ENTEH Low-NOx pyrolysis gas burners (45 MW each).

Project Overview

Major reconstruction of the TP-101 power boiler featuring the installation of four ENTEH Low-NOx pyrolysis gas burners rated at 45 MW each (180 MW total capacity). The engineering solution delivers optimal combustion efficiency for shale pyrolysis off-gas while keeping nitrogen oxide emissions well within environmental limits.

Key Specifications

  • Client / Facility: Enefit Power AS
  • Boiler Unit: Power boiler TP-101
  • Burner Capacity: 4 burners × 45 MW (180 MW total)
  • Fuel Type: Shale pyrolysis gas (retort gas)
  • Technology: ENTEH Low-NOx staged combustion
  • Scope: Engineering, fabrication, supply, installation, and complete commissioning
Enefit Power AS TP-101 Boiler Upgrade
We use cookies
We use essential cookies to make our website work properly. Optional cookies and external services, such as Google Maps, may be used with your permission. You can accept or reject optional cookies, or manage your preferences in Cookie Settings.