Enefit Green AS (Paide CHP) — Installation of 5 MW start-up burner on fluidized bed boiler

Installation of 5 MW start-up burner on Paide CHP fluidized bed boiler.

Project Overview

Installation and integration of a 5 MW start-up burner for the bubbling fluidized bed (BFB) boiler at Paide CHP plant. The system provides controlled furnace and bed preheating during boiler cold/warm start-ups and supports flame stabilization during main biofuel quality fluctuations.

Key Specifications

  • Client / Facility: Enefit Green AS (Paide CHP Plant)
  • Boiler Unit: Fluidized Bed Boiler (BFB)
  • Application: Start-up / ignition burner
  • Thermal Capacity: 5 MW
  • Scope: Equipment supply, mechanical installation, control system integration, and commissioning
Enefit Green AS Paide CHP Start-up Burner Installation