EPC contract for dry ash removal system on BKZ-75-39FSl boiler (250 m pneumatic transport).

Project Overview

Turnkey EPC project for design, procurement, and construction of a modern dry pneumatic fly ash removal system for the BKZ-75-39FSl boiler at VKG Energia OÜ. The system enables efficient ash collection and pneumatic transport over a distance of 250 meters to the storage silo.

Key Specifications

  • Client: VKG Energia OÜ
  • Equipment: BKZ-75-39FSl boiler
  • System Type: Pneumatic ash transport
  • Transport Distance: 250 m